TCN, NISO, Other Stakeholders Coordinate Outage, Load Diversion on Kumbotso–Dan Agundi 132kV Line
TCN, NISO, Other Stakeholders Coordinate Outage, Load Diversion on Kumbotso–Dan Agundi 132kV Line
The Transmission Company of Nigeria (TCN), Kano Region, held a coordination meeting with Nigerian Independent System Operator (NISO), Kano Electricity Distribution Company (KEDCO), project contractors, and Kano State Ministry of Works to discuss a proposed outage and load diversion for the elongation of Towers 27 and 28 on the Kumbotso–Dan Agundi 132kV Transmission Line.
The meeting, held on Monday, October 5, 2026, at the Regional Conference Room, Kano, was chaired by General Manager (Transmission), Kano Region, Engr. M. K. Bello.
In his opening remarks, Engr. Bello expressed confidence in the contractors’ competence but emphasized that they must thoroughly assess all proposed technical connections and switching arrangements before implementation to ensure operational safety and network reliability.
Speaking, NISO Regional Operations Coordinator (ROC), Engr. Kunle Egbedinni, stressed the need for strict Grid Code compliance, particularly the requirement to submit planned outage applications at least 14 days in advance for approval.
Following this, Head, Operations and Maintenance, KEDCO, Engr. Sabiu Haruna proposed diverting the load served by Dan Agundi 132kV Substation to alternative substations, including Dakata 132kV, Tamburawa 132kV, Rimin Zakara 330kV, Kumbotso 330kV, and Wudil 132kV substations, within a proposed two-day outage window.
Participants reviewed network capacity and alternative supply arrangements for the exercise. They observed that Hadejia 132kV Substation could not absorb the full 60MW load earmarked for diversion, and assessed supply options from the Tamburawa, Rimin Zakara and Dakata substations. They also emphasised the need to ensure the safety of personnel and equipment.
The meeting concluded with all stakeholders committing to strengthen inter-agency coordination, ensure regulatory compliance, and facilitate timely project execution.